Project Details
Work Type Repaving and Reconstruction
Phase Construction
Limits from east of SR 50A to west of Live Oak Drive
Project Start September 2017
Length .33 miles
City
  • Brooksville
County
  • Hernando
Road
  • Cortez Blvd
  • SR 50
  • SR 50A
  • US 98
Construction Cost $4.7 million
Estimated Completion late summer 2018
Contractor Commercial Industrial Corporation
Contact Information
Construction Manager
Zach Stringer
352-848-2600
Zachary.Stringer@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
About

The Florida Department of Transportation's contractor, Commercial Industrial Corporation, is repaving and reconstructing US 98/SR 50 (Cortez Boulevard) from east of SR 50A to west of Live Oak Drive in Hernando County.

Improvements include:

  • Replacing sections of asphalt at the intersection with concrete to better handle the heavy truck traffic in this area
  • Repaving the remaining section of roadway with asphalt
  • Adding sidewalk to both sides of the roadway 

Motorists are advised that traffic shifts and lane closures will be required to build this project. Work requiring lane closures may occur nightly from 7:00 to 7:00 am. 

Electronic message boards will alert motorists to the upcoming closures. 

This $4.7 million project is anticipated to finish in late summer of 2018.