EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type Bridge Replacement
Phase Completed
Limits from west of Halls River to east of Halls River
Length .33 miles
City
County
Road
About

FINAL ACCEPTED ON JANUARY 21, 2020

The new 57-foot wide bridge will be made of state of the art rust-resistant materials and built in the same location as the previous 30-foot wide bridge. It will feature a 12-foot travel lane in each direction, eight-foot shoulders, and five-foot sidewalks.

Traffic is now using half of the new bridge and shoulder in a temporary two-way configuration while the second half of the new bridge is built.

Motorists are advised to use caution while traveling through the work zone. Access to driveways and side streets are being maintained.

The $7.6 million project is expected to finish in the fall of 2019. 

View Factsheet
Contact Information
Media Contact
David Botello
813-975-6060
David.Botello@dot.state.fl.us
Closures
  • There are no closures at this time.
Project Files
Project Images
Halls River Bridge Project November 2019
Halls River Bridge Project November 2019
Halls River Bridge Project November 2019
Halls River Bridge Project November 2019
Halls River Bridge Project November 2019
Halls River Bridge Project November 2019
Halls River Bridge Project October 2019
Halls River Bridge Project October 2019
Halls River Bridge Project September 2019
Halls River Bridge Project September 2019
Halls River Bridge Project September 2019
HRB - Setting UP Bridge Deck Grinding Machine Sept. 2019
HRB - Checking Bridge Deck for Smoothness Sept. 2019
HRB - Bridge Deck Grinding Machine Sept. 2019
HRB - Forming North Traffic Railing with White Cement Sept. 2019
Halls River Bridge Project September 2019
Halls River Bridge Project September 2019
Halls River Bridge Project September 2019
Halls River Bridge Project September 2019
Halls River Bridge Project September 2019
Halls River Bridge Project September 2019
Halls River Bridge Project September 2019
Halls River Bridge Project August 2019
Halls River Bridge Project August 2019
Halls River Bridge Project August 2019
Halls River Bridge Project August 2019
Halls River Bridge Project August 2019
Halls River Bridge Project July 2019
Halls River Bridge July 2019
Halls River Bridge July 2019
Halls River Bridge July 2019
Halls River Bridge July 2019
Halls River Bridge July 2019
Halls River Bridge Project July 2019
Halls River Bridge Project July 2019
Halls River Bridge Project June 2016
Halls River Bridge Project June 2016
Halls River Bridge Project -- June 2019
Halls River Bridge June 2019
Halls River Bridge Deck Pour May 2019
Halls River Bridge Deck Pour May 2019
Halls River Bridge Deck Pour May 2019
Halls River Bridge Deck Pour May 2019
Halls River Bridge Deck Pour May 2019
Halls River Bridge Deck Pour May 2019
Halls River Bridge May 2019 Placing and Tying Deck Reinforcement
Halls River Bridge May 2019 Barrier Wall Prep Work
Halls River Bridge Recently Poured Concrete Slope March 2019
Halls River Bridge Placed Beams March 2019
Halls River Bridge Placing Concrete for Slope Pavement March 2019
Halls River Bridge Removing Turbidity Curtain March 2019
Halls River Bridge Filling Frame with Concrete February 2019
Halls River Bridge Inside Look of Bridge Frame February 2019
Halls River Bridge Underground Concrete Structures for Future Sheet Pile Wall February 2019
Halls River Bridge Preparing Road Base Jan 2019
Halls River Bridge Recently Removed Forms from Bulkhead Walls Jan 2018
Halls River Bridge Continue Work on Bridge Piers Dec 2018
Halls River Bridge Securing Form for Top of Sheet Pile Wall Dec 2018
Halls River Bridge Removing Barrier Wall to Allow Roadway Construction Dec 2018
Halls River Bridge Pier Work Continues Mid Nov 2018
Halls River Bridge Forming Top of Concrete Wall (Westside) Mid Nov 2018
Halls River Bridge Reinforcements for Intermediate Bents Mid Nov 2018
Halls River Bridge Placing Friction Collars on Piers Nov 2018
Halls River Bridge Cutting Concrete Sheet Pile Panels Nov 2018
Halls River Bridge Preperation of Reinforcements for Intermediate Bents Nov 2018
Halls River Bridge Constructing Concrete Sheet Pile Wall on WB Section of New Bridge October 2018
Halls River Bridge Cutting Sheet Pile Wall on WB Section of New Bridge October 2018
Halls River Bridge Installing Concrete Panels on WB Section of New Bridge October 2018
Halls River Bridge Extracting Substructure (Old Piles) August 2018
Halls River Bridge Removing Intermediate Bents August 2018
Halls River Bridge Removing Old Bridge Deck August 2018
Halls River Bridge Project Buidling Gravity Wall August 2018
Preparing roadway for paving (entrance to Marguerita Grill) August 2018
Two-way Traffic on Halls River Bridge July 2018
Constructing Slopes Walls June 2018
Prepping New Roadway for Paving June 2018
Grading Westbound Approach to Halls River Bridge June 2018
Halls River Bridge Concrete Deck Pour May 2018
Halls River Bridge Concrete Deck Pour II May 2018
Halls River Bridge Concrete Deck Pour III May 2018
Halls River Bridge Concrete Deck Pour IV May 2018
Halls River Bridge Concrete Deck Pour V May 2018
Halls River Bridge Concrete Deck Pour VI May 2018
Newly Installed Glass Fiber Reinforced Polymer (GFRP) May 2018
Crews inpect bridge deck before placing concrete deck May 2018
Constructing embankment for new bridge approach May 2018
Halls River Bridge Stay-In-Place forms April 2018
Halls River Bridge Installing Ovehang Jacks & Decking April 2018
Halls River Road Bridge Work April 2018
Halls River Road Bridge April 2018
Halls River Road Drainage Improvements April 2018
Halls River Bridge I January 2018
Halls River Bridge II January 2018
Halls River Bridge Replacement Project November 2017
Halls River Bridge Deck November 2017
Halls River Bridge Road Widneing November 2017
HRB Jan 2017 2
HRB Jan 2017 3
HRB Jan 2017 4
Halls River Bridge February 2017
HRB Jan 2017 1
Halls River Bridge February 2017 (3)
Halls River Bridge February 2017 (2)
Halls River Bridge February 2017 (5)
Halls River Bridge February 2017 (4)