Project Details
Work Type Bridge Replacement
Phase Construction
Limits from west of Halls River to east of Halls River
Project Start January 2017
Length .33 miles
City
County
Road
Construction Cost $7.5 million
Estimated Completion Spring 2019
Contractor Astaldi Construction Corporation
About

The existing 60-year-old Halls River Bridge is being replaced!

The new 57-foot wide bridge will be made of state of the art rust-resistant materials and built in the same location as the previous 30-foot wide bridge.

The new wider bridge will feature a 12-foot travel lane in each direction, eight-foot shoulders, and five-foot sidewalks.

The new bridge is being built in phases.

Traffic is now using half of the new bridge and shoulder in a temporary two-way configuration while the second half of the new bridge is built.

Construction activities are occurring during the day Monday through Friday from 7:30 a.m. to 6 p.m.and Saturdays when necessary.

Motorists are advised to use caution while traveling through the work zone. Access to driveways and side streets are being maintained.

The $7.5 million project is expected to finish in spring 2019. 

View Factsheet
Contact Information
Construction Manager
Zachary Stringer
352-848-2651
Zachary.Stringer@dot.state.fl.us
Media Contact
David Botello
813-975-6060
David.Botello@dot.state.fl.us
Lane Closures
  • Halls River Road (CR 490A) bridge replacement from Hadley Court to Taylor Terrace
    Intermittent lane closures: Monday, November 19 through Wednesday, November 21 from 7:30 a.m. to 6 p.m.

Project Files
Project Images
Halls River Bridge Constructing Concrete Sheet Pile Wall on WB Section of New Bridge October 2018
Halls River Bridge Cutting Sheet Pile Wall on WB Section of New Bridge October 2018
Halls River Bridge Installing Concrete Panels on WB Section of New Bridge October 2018
Halls River Bridge Extracting Substructure (Old Piles) August 2018
Halls River Bridge Removing Intermediate Bents August 2018
Halls River Bridge Removing Old Bridge Deck August 2018
Buidling Gravity Wall August 2018
Preparing roadway for paving (entrance to Marguerita Grill) August 2018
Two-way Traffic on Halls River Bridge July 2018
Constructing Slopes Walls June 2018
Prepping New Roadway for Paving June 2018
Grading Westbound Approach to Halls River Bridge June 2018
Halls River Bridge Concrete Deck Pour May 2018
Halls River Bridge Concrete Deck Pour II May 2018
Halls River Bridge Concrete Deck Pour III May 2018
Halls River Bridge Concrete Deck Pour IV May 2018
Halls River Bridge Concrete Deck Pour V May 2018
Halls River Bridge Concrete Deck Pour VI May 2018
Newly Installed Glass Fiber Reinforced Polymer (GFRP) May 2018
Crews inpect bridge deck before placing concrete deck May 2018
Constructing embankment for new bridge approach May 2018
Halls River Bridge Stay-In-Place forms April 2018
Halls River Bridge Installing Ovehang Jacks & Decking April 2018
Halls River Road Bridge Work April 2018
Halls River Road Bridge April 2018
Halls River Road Drainage Improvements April 2018
Halls River Bridge I January 2018
Halls River Bridge II January 2018
Halls River Bridge Replacement Project November 2017
Halls River Bridge Deck November 2017
Halls River Bridge Road Widneing November 2017
HRB Jan 2017 2
HRB Jan 2017 3
HRB Jan 2017 4
Halls River Bridge February 2017
HRB Jan 2017 1
Halls River Bridge February 2017 (3)
Halls River Bridge February 2017 (2)
Halls River Bridge February 2017 (5)
Halls River Bridge February 2017 (4)