Project Details
Work Type Widening
Phase Construction
Limits from CR 581 (Bellamy Brothers Road) to Old Pasco Road
Project Start November 28, 2016
Length 1.5 miles
City
County
Road
Construction Cost $12.6 million
Estimated Completion Late 2018
Contractor D.A.B. Constructors
About

D.A.B. Constructors, Inc., on behalf of the Florida Department of Transportation, is widening approximately 1.5 miles of State Road 52 (Schrader Highway) between CR 581 (Bellamy Brothers Boulevard) and Old Pasco Road from a two lane road to a four lane divided roadway with medians in Pasco County.

Other improvements include installing a new traffic signal at Old Pasco Road, replacing the traffic signal at Bellamy Brothers Boulevard, constructing a 12 foot multi-use path along the north side of the road and a 5 foot sidewalk on the south side.    

Most construction activities are taking place during daytime hours.

The $12.6 million project began in late November 2016 and is expected to finish in late 2018. 

View Factsheet
Contact Information
Construction Manager
Mike Kopotic
813-975-3552
Michael.Kopotic@dot.state.fl.us
Media Contact
John McShaffrey, APR
813-975-6930
John.McShaffrey@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Project Files
Project Images
SR 52 Widening Pasco 8
SR 52 Widening Pasco 8
The widened SR 52 corridor taking shape - March 2017
The widened SR 52 corridor taking shape - March 2017
Drainage pipe ready for unloading - March 2017
Drainage pipe ready for unloading - March 2017
SR 52 Widening Pasco 6
SR 52 Widening Pasco 6
SR 52 Widening Pasco 3
SR 52 Widening Pasco 3
Construction begins on SR 52 east of Old Pasco Road - December 2016
Construction begins on SR 52 east of Old Pasco Road - December 2016
Drainage pipe and utility relocations at SR 52 and Bellamy Bros. Rd. - February 2017
Drainage pipe and utility relocations at SR 52 and Bellamy Bros. Rd. - February 2017
Storm water drainage pipe installation on the north side of SR 52 - March 2017
Storm water drainage pipe installation on the north side of SR 52 - March 2017
SR 52 Widening Pasco 5
SR 52 Widening Pasco 5
SR 52 Widening Pasco 9
SR 52 Widening Pasco 9
SR 52 Widening Pasco 7
SR 52 Widening Pasco 7
SR 52 Widening Pasco
SR 52 Widening Pasco
Unloading & stacking pipe - March 2017
Unloading & stacking pipe - March 2017
SR 52 Widening Pasco 4
SR 52 Widening Pasco 4
SR 52 Widening Pasco 2
SR 52 Widening Pasco 2
Clearing for roadway widening on the north side of SR 52 - January 2017
Clearing for roadway widening on the north side of SR 52 - January 2017