Project Details
Work Type Widening
Phase Construction
Limits from W. Green Acres Street to S. Jump Court
Project Start November 7, 2016
Length 2.1 miles
City
County
Road
Construction Cost $28.6 million
Estimated Completion Summer 2020
Contractor D.A.B. Constructors, Inc.
About

The Florida Department of Transportation’s contractor is widening and reconstructing US Highway 19 in Homosassa Springs from four lanes to a six-lane divided highway from West Green Acres Street to West Jump Court.

The improvements will take place within the existing rights of way and will increase roadway capacity and improve safety along the corridor. Among the improvements are adding an additional lane in each direction with paved shoulders, designated bike lanes on the paved shoulders, and sidewalks on both sides of US 19.
 

Improvement Highlights

  • Widen US 19 from 4 to 6 lanes.
  • New sidewalks and designated bicycle lanes.
  • Improve street lighting, traffic signals, and drainage.


Lane Closure Hours
8:00 p.m. to 7:00 a.m.

View Factsheet
Contact Information
Construction Manager
Tyler Matthews
813-975-3560
Tyler.Matthews@dot.state.fl.us
Media Contact
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Lane Closures
  • US 19 from Yulee Drive to north of Homosassa Trail
    Night lane closures: Monday, March 18 through Friday, March 22 from 8 p.m. to 7 a.m.

Project Files
Project Images
Widening work is focused on the west side of the US 19 corridor in Homosassa Springs (June 2018 photo)
US 19 traffic has been shifted to the east side of the corridor near the US Post Office to focus on widening work on the west side (June 2018 photo)
US 19 near Homosassa Springs Wildlife State Park - November 2016
Temporary pavement construction near post office - March 2017
Early construction - November 2016
Looking southwest towards south end of project - February 2017
Early clearing near south end of project - February 2017
First month of construction - south end - November 2016
Drainage pond being built at north end of project - March 2017
Construction near Homosassa Trail - January 2017
Central project area - November 2016