Project Details
Work Type Repaving
Phase Construction
Limits Toucan Trail to Cortez Boulevard
Project Start late-March
Length 3.5 miles
City
County
Road
Construction Cost $13 million
Estimated Completion Summer 2018
Contractor D.A.B. Constructors, Inc
About

The Florida Department of Transportation’s contractor, D.A.B. Constructors, Inc., is repaving approximately 3.5 miles of US 19 (Commercial Way) between Toucan Trail and Cortez Boulevard (SR 50) in Hernando County.

Other improvements include installing a new traffic signal at Toucan Trail, adding a sidewalk to both sides of the roadway, cleaning drainage pipes where needed, and modifying the median opening to allow only left turns at Pacific Avenue / Williams Street.  

Construction activities and lane closures will occur during daytime and nighttime hours. Access to driveways and side streets will be maintained during construction.

The $13 million project is expected to finish in the summer of 2018.

View Factsheet
Contact Information
Construction Manager
Tyler Matthews
352-848-2600
Tyler.Matthews@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Project Files
Project Images
US 19 Nighttime Paving May 2018
US 19 Nighttime Paving II May 2018
New Signal at Toucan Trail is now active
US 19 Removing Sections of Roadway
US 19 Newly Poured Sidewalk
US 19 New Sidewalk
US 19 Future Traffic Signal at Toucan Trail