US 19 Widening from Jump Court to Fort Island Trail 405822-3-52-01
Project Details
Work Type | Widening |
---|---|
Phase | Construction |
Limits | From Jump Court to Fort Island Trail |
Project Start | November 2018 |
Length | 4.7 miles |
City | |
County | |
Road | |
Construction Cost | $52.9 million |
Estimated Completion | Summer 2024 |
Contractor | PCS Civil, Inc. |
About
This project is widening US 19 from four lanes to six lanes between S. Jump Court and W. Fort Island Trail in Citrus County. A shared use path, sidewalks, and storm water ponds are also being constructed with this project.
_________________________________________
Progress Update > Traffic Shifted to New Alignment on Southbound US 19
Construction reached another milestone on October 18, 2023, with southbound traffic now shifted to new pavement from W Fort Island Trail to south of W Venable Street. Traffic is now in the final alignment with a median separating northbound and southbound US 19 travel lanes throughout the project area from S Jump Court to W Fort Island Trail. Both directions remain two lanes in each direction, with third lanes expected to open in spring/summer 2024.
_________________________________________
* Construction cost includes original construction contract amount plus approved contract changes. It does not include inspection oversite.
Contact Information
Project Information |
---|
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
kristen.carson@dot.state.fl.us
|
Closures
-
US 19 from S. Jump Court to W. Fort Island Trail
Day lane closures: Sunday, March 24 through Saturday, March 30 from 7 a.m. to 6:30 p.m.
Night lane closures: Sunday, March 24 through Friday, March 29 nights from 6:30 p.m. to 7 a.m.