Project Details
Work Type Repaving
Phase Construction
Limits From east of Ashley Drive to west of Nebraska Avenue
Project Start August 2018
City
County
Road
Construction Cost $1.6 million
Estimated Completion Early 2019
Contractor Ajax Paving Industries, Inc.
About

The Florida Department of Transportation's contractor, Ajax Paving Industries, Inc., is repaving the westbound lanes on Kennedy Blvd (SR 60) between Ashley Drive and Nebraska Avenue in Downtown Tampa.

Other improvements include upgrading the sidewalks in areas along the corridor. This work will require intermittent closures of the sidewalks. 

Construction activities are occurring during daytime and nighttime hours. Lane closures are taking place Monday through Friday from 10 a.m. to 5 p.m. 

This project is expected to finish in early 2019.

View Factsheet
Contact Information
Construction Manager
Tom Curley
813-612-3200
Thomas.Curley@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • SR 60 (Kennedy Boulevard) repaving from Nebraska Avenue to Florida Avenue
    Lane closures: Monday, January 14 through Thursday, January 17 from 10 a.m. to 6 p.m. and from 7 p.m. to 7 a.m.

Project Files
Project Images
Kennedy Blvd. New Sidewalk Pavers December 2018
Kennedy Blvd. Sidewalk Installation Dec 2018
Kennedy Blvd. Drainage Work Dec 2018