Project Details
Work Type Traffic Signal Upgrades
Phase Construction
Limits From Armenia Avenue to Brevard Avenue
Project Start Fall 2019
City
County
Road
Construction Cost $2.1 million
Estimated Completion Summer 2020
Contractor Contact Network, LLC
About

This project will replace the existing traffic signals on SR 60 ( Kennedy Blvd) with hurricane resistant poles at Armenia, Howard, Willow and Brevard avenues.  A new signal will be installed at Rome Avenue as well.

Construction is anticipated to begin in the fall of 2019 and be complete in the summer of 2020.

View Factsheet
Contact Information
Construction Manager
Tom Curley
813-612-3200
Thomas.curley@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.