Project Details
Work Type Widening
Phase Construction
Limits From Suncoast Parkway to US 41 at Ayers Road
Project Start September 2019
Length 2.9 miles
City
County
Road
Construction Cost $20.2 million
Estimated Completion Summer 2022
Contractor Watson Civil Construction, Inc.
About

This project will create a new four-lane roadway connecting CR 578 (County Line Road)  to Ayers Road (CR 576) at US 41. The project will widen County Line Road between the Suncoast Parkway and the new Ayers Road connection. 

As part of the new Ayers Road project, an 11-foot wide multi-use path will be built on the north side of CR 578 and the west and north sides of the new Ayers Road. The multi-use path will connect to the Suncoast Trail. 

New traffic signals will be installed at both intersections of Trillium Blvd. and Ayers Road and at the intersection of Ayers Road and US 41.

The 2.9-mile project is just north of the Pasco/Hernando County line. It begins east of the Suncoast Parkway and ends at US 41 at Ayers Road in Masaryktown.

Construction is anticipated to finish summer of 2022. 

View Factsheet
Contact Information
Construction Manager
Cleo Babb
352-848-2600
Cleo.babb@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Project Files
Project Images
Fence installation near pond -- February 2020
Pond excavation --- February 2020
Embankment work --- February 2020
Drainage installation at Trillium Blvd - February 2020
Clearing Operation at Southend of the project --- February 2020
Clearing Operation --- January 2020
Drainage Pipe Installation --- January 2020
Head Wall Placement --- January 2020
Filter Fabric Installation --- January 2020
Drainage Installation Work --- January 2020
Drainage Pipe Installation Work --- January 2020
Pipe installation at future pond - January 2020
Clearing and Grubbing Near Trillium Development - Janaury 2020
Prep work of future roadway - January 2020
Clearing operation at Future Pond January 2020
Ayers Road Extension (CR 576) New Roadway and Widening Project - December 2019
Ayers Road Extension (CR 576) New Roadway and Widening Project - December 2019
Ayers Road Extension (CR 576) New Roadway and Widening Project - December 2019
Ayers Road Extension (CR 576) New Roadway and Widening Project - December 2019
Ayers Road Extension (CR 576) New Roadway and Widening Project - December 2019
Ayers Road Extension (CR 576) New Roadway and Widening Project - December 2019
Silt Fence Installation - October 2019
Silt Fence Installation --- October 2019
Silt Fence Layout - October 2019
Clearing Work Continues --- October 2019
Silt Fence Installation at Pond 5 --- October 2019
Silt Fence Installation --- October 2019
Clearing work continues --- October 2019
Clearing work continues --- October 2019
Clearing work continues --- October 2019
Clearing work continues --- October 2019
Clearing work continues --- October 2019
Clearing work continues --- October 2019
Clearing work continues --- October 2019
Clearing work has begun --- October 2019
Clearing work has begun --- October 2019
CR 578 at Ayers Road Public Meeting September 2018 one
CR 578 at Ayers Road Public Meeting September 2018 three
CR 578 at Ayers Road Public Meeting September 2018 two
CR 578 at Ayers Road Public Meeting September 2018 one