Project Details
Work Type Drainage Improvements
Phase Completed
Limits From west of Hoover Boulevard to Hoover Boulevard
Length 1300 feet
City
County
About

THIS PROJECT RECEIVED FINAL ACCEPTANCE ON APRIL 23, 2019. 

The $5.6 million project will re-grade and stabilize the canal slopes for a distance of approximately 1300 feet along the Henry Canal west of Hoover Boulevard in Hillsborough County.

Improvements will resolve the slope stability and erosion issues along the drainage canal.

Construction is expected to finish in the spring of 2019. 

View Factsheet
Contact Information
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.
Project Images
Henry Street Canal Drainage Improvement Project June 2018 one
Henry Street Canal Drainage Improvement Project June 2018 two
Henry Street Canal Drainage Improvement Project June 2018 three
Henry Street Canal Drainage Improvement Project June 2018 four
Henry Street Canal Drainage Improvement Project June 2018 five
Henry Street Bridge Canal Project April 2018
Henry Street Bridge Canal Project II April 2018