EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type Highway Lighting Upgrades
Phase Completed
Limits US 92 - 16 intersections, SR 60 - 3 intersections
City
County
Road
About

FINAL ACCEPTED: JUNE 9, 2019

This project will upgrade the highway lighting at numerous intersections throughout Pinellas County: 

  • US 92 - 16 intersections between 3rd Avenue South and 83rd Avenue North in St. Petersburg
  • SR 60 - 3 intersections between US 19 and Park Place in Clearwater

Construction is anticipated to finish in the spring of 2019.

View Factsheet
Contact Information
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.