Project Details
Work Type Highway Lighting Upgrades
Phase Construction
Limits US 92 - 16 intersections, SR 60 - 3 intersections
Project Start January 2019
City
County
Road
Construction Cost $498,000
Estimated Completion Summer 2019
Contractor Florida Safety Contractors, Inc.
About

This project will upgrade the highway lighting at numerous intersections throughout Pinellas County: 

  • US 92 - 16 intersections between 3rd Avenue South and 83rd Avenue North in St. Petersburg
  • SR 60 - 3 intersections between US 19 and Park Place in Clearwater

Construction is anticipated to finish in the spring of 2019.

View Factsheet
Contact Information
Construction Manager
Sarah Gansz
727-575-8300
Sarah.Gansz@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • SR 60 (Gulf to Bay Boulevard) intersection lighting improvements from US 19 to Park Place
    Lane closures: Sunday, March 17 through Thursday, March 21 from 10 p.m. to 6 a.m.

  • SR 687 (4th Street) intersection lighting improvements from 30th Avenue North to 83rd Avenue North
    Lane closures: Sunday, March 17 through Thursday, March 21 from 8:00 p.m. to 8 a.m.