SR 50 (Cortez Boulevard) Widening from Cobb Road to west of Buck Hope Road 416733-2-52-01
Project Details
Work Type | Widening |
---|---|
Phase | Construction |
Limits | From Cobb Road to west of Buck Hope Road |
Project Start | April 3, 2023 |
Length | 1.3 miles |
City | |
County | |
Road | |
Construction Cost | $15.8 million |
Estimated Completion | Early 2025 |
Contractor | PCS Civil, Inc. |
About
This project is widening SR 50 (Cortez Boulevard) between Cobb Road and Buck Hope Road from four lanes to six lanes. The intersection of Cobb Road / W Jefferson Street / SR 50 will be rebuilt in concrete.
During the construction phase when the intersection is rebuilt, there will be around-the-clock lane closures. One lane will be open in each direction during the intersection reconstruction. Periodic lane closures will be scheduled as needed throughout the project area.
Other project improvements include milling and resurfacing the existing roadway, installing curb and gutter, drainage improvements, adding bicycle lanes, and building sidewalks.
Construction is underway as of April 3, 2023.
Contact Information
Project Information |
---|
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
-
SR 50 (Cortez Blvd.) from Jefferson Street to west of Buck Hope Road
Lane closures (westbound): Monday, March 25 through Friday, March 29 from 7 a.m. to 4:30 p.m. -
SR 50 (Cortez Blvd.) eastbound from east of Mobley Road to Cobb Road
One lane closed: 24 hours per day, until further notice