EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type Interchange improvement
Phase Design
Limits I-75 NB on ramp from NB US 301
City
County
Road
Design Cost $742,000
About

This project will widen the current on-ramp from NB US 301 to NB I-75 from one to two lanes. The project is in the Brandon area of Hillsborough County.

The project is scheduled to begin construction in 2025.

View Factsheet
Contact Information
Design Manager
Manuel Flores
813-975-4248
Manuel.flores@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.