Work Type Adding Pedestrian Signals
Phase Construction
Limits 64/63rd Street, 60th Way/Street and 56/55th Way
Project Start July 2019
Length at various locations
City
County
Road
Construction Cost $862,163
Estimated Completion Fall 2019
Contractor Ajax Paving Industries of Florida, LLC
About

This design-build project is making safety improvements that include the installation of a High-Intensity Activated Crosswalk (HAWK) in the median with pedestrian-actuated lighting at three locations along SR 694 (Park Boulevard) at 64/63rd Street, 60th Way/Street and 56/55th Way in Pinellas County.    

Motorists should expect intermittent daytime and nighttime lane closures. 

This project is expected to finish fall of 2019. 

View Factsheet
Contact Information
Construction Manager
Randall Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.