Project Details
Work Type Widening
Phase Design
Limits from south of SR 56 to south of SR 39
Length 2 miles
City
County
Road
Design Cost $2.5 million
ROW Cost $11.1 million
About

This project will widen US 301 from two lanes to a four lane divided road with medians, bike lanes, a sidewalk on the east side and a shared use path on the west side.

Design is underway. Right of way acquisition will begin in 2020. Construction is not funded at this time.

 

View Factsheet
Contact Information
Design Manager
Jake Hemingway
813-975-6057
jake.hemingway@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.