Project Details
Work Type ITS Installation for Wrong-way Detection
Phase Construction
Limits I-4 off-ramps at SR 33/CR 582
Project Start June 2018
City
Road
Construction Cost $372,108
Estimated Completion Fall of 2019
Contractor Ajax Paving Industries of Florida
About

The Florida Department of Transportation's Design-Build Firm, Ajax Paving Industries of Florida, is installing Intelligent Transportation System (ITS) fiber for wrong-way detection at I-4 off-ramps at SR 33/CR 582 in Polk County. 

In recent years, the Department has been installing these sites throughout the District as a safety measure to help prevent wrong-way events. These sites consist of a static sign and red flashing beacons that turn on when a motorist travels in the opposite direction of traffic with an automated alert to the FDOT District 7 SunGuide Center with the actuation of a wrong-way event. 

Nightly lane closures may occur from 11 p.m. to 5 a.m.

This project is expected to finish in the fall of 2019.

View Factsheet
Contact Information
Construction Manager
Randall Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.