Project Details
Work Type Bridge Maintenance
Phase Construction
Limits I-275, I-4, I-75
Project Start February 2020
City
County
Road
Construction Cost $555,000
Estimated Completion Early 2021
Contractor Seminole Equipment, Inc.
About

This project will paint the steel girders, piers and bearings on the I-275 bridges over Central Avenue and on the eastbound I-4 ramp to northbound I-75 in Tampa.

Construction is expected to finish in early 2021.

View Factsheet
Contact Information
Construction Manager
Andrew Williams
813-612-3200
Andrew.Williams@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • I-4 westbound and eastbound at I-75
    Lane closures: Monday, June 1 through Saturday, June 6 from 7 p.m. to 6 a.m.