EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Phase Construction
Limits I-275 from east of the Howard Frankland Bridge to east of Lois Avenue
Project Start March 2019
Length 2.4 miles
City
County
Road
Construction Cost $31 Million
Estimated Completion Early 2021
Contractor The Middlesex Corporation
About

Construction is underway on the I-275 corridor to improve operations of the I-275 / SR 60 interchange and I-275 from east of the Howard Frankland Bridge to Lois Avenue. These improvements are designed to provide congestion relief by adding lanes to I-275.

Here are the planned improvements:

  • Add a lane in both directions of I-275 between the exit ramps to SR 60 and the entrance ramps from SR 60
  • Add a lane to the northbound I-275 exit ramp to SR 60  
  • Remove the merge from the eastbound SR 60 loop ramp onto northbound I-275 by adding a lane onto I-275
  • Add a lane and noise wall barrier on northbound I-275 between West Shore Boulevard and Lois Avenue
  • Widen the ramp from SR 60 onto southbound I-275 

This project is a design-build project, which means that an overall concept of the design was put out to bid with many design requirements specified in a Request for Proposals. The successful contractor was chosen from a number of qualified firms bidding on the contract based on a design that met the requirements and is the most economical to construct. The contracting team that was selected is responsible for the final design (with its own or contracted licensed engineers) under the same contract time that includes the construction. This allows the contractor to begin working on specific items of work as portions of the design are completed and approved. Construction work was underway as of June 2019.

View Factsheet
Contact Information
Construction Manager
Tom Lay
813-975-3554
tom.lay@dot.state.fl.us
Media Contact
John McShaffrey, APR
813-975-6930
John.McShaffrey@dot.state.fl.us
Lane Closures
  • SR 60 under I-275
    Day lane closures: Monday, April 6 through Saturday, April 11 from 7 a.m. to 4 p.m.
    Night lane closures: Monday, April 6 through Friday, April 10 from 9 p.m. to 5 a.m.

  • I-275 from west of SR 60 (Exit 39) to Lois Avenue (Exit 40B)
    Lane closures: Monday, April 6 through Friday, April 10 from 9 p.m. to 5 a.m.

  • West Shore Boulevard (CR 587) at I-275
    Day lane closures: Monday, April 6 through Saturday, April 11 from 7 a.m. to 4 p.m.
    Night lane closures: Monday, April 6 through Friday, April 10 from 9 p.m. to 5 a.m.

Project Files
Project Images
All beams have been installed for the widening of the northbound I-275 bridge over SR 60 (3/21/2020 photo)
Crews were busy in the early morning installing concrete beams at I-275 over SR 60 (3/21/2020 photo)
A beam is lowed into place by crane and guided by workers at I-275 over SR 60 (3/21/2020 photo)
A car on northbound I-275 passes by workers installing bridge beams over SR 60 (3/21/2020 photo)
Workers install a bridge beam at SR 60 next to northbound I-275 (3/21/2020 photo)
Workers guide a concrete beam into place where the northbound I-275 bridge is being widened over Sr 60 (3/21/2020 photo)
A crane lifts a concrete beam into place at SR 60 and I-275 (3/21/2020 photo)
A concrete beam is lifted by crane off a transport truck at SR 60 and I-275 (3/21/2020 photo)
Crews place a concrete beam over SR 60 where the northbound I-275 bridge is being widened (3/20/2020 photo)
Work on a pier for northbound I-275 bridge widening over SR 60
Workers prepare a pier for beams that will be set soon over SR 60 (3/16/20 photo)
Form work for a noise barrier wall along northbound I-275 (3/16/20 photo)
Workers place concrete between the West Shore Boulevard entrance ramp and the northbound I-275 lanes (3/16/20 photo)
Detour map for closure of northbound West Shore Blvd.
Detour map for full closure of SR 60 at I-275
Detour Map for Closure of I-275 in Westshore area
Widening work on northbound I-275 on the Tampa side of the Howard Frankland Bridge (2-18-20 photo)
A pier cap being is being formed at I-275 and West Shore Boulevard during the early morning on February 25, 2020.
A pier cap being is being formed at I-275 and West Shore Boulevard during the early morning on February 25, 2020.
Detour map for closure of northbound I-275 between SR 60 and Lois Avenue
Lowering a reinforcing steel cage into a drilled shaft prior to placing concrete in the shaft
Working on the seawall on the south side of I-275 east of the Howard Frankland Bridge
Workers install pipe in a trench box next to I-275
Workers tie steel for noise barrier wall
Workers tie steel for noise barrier wall
Workers prepare forms for noise barrier wall
Pile installation next to northbound I-275 at West Shore Boulevard
Detour map for closure of West Shore Blvd. ramps onto northbound I-275
Detour Map for around-the-clock closure of northbound West Shore Boulevard under I-275
Detour Map for closure of Northbound West Shore Boulevard under I-275
Map of detour route for closure of westbound SR 60 under I-275
Detour Map for closure of West Shore Boulevard under I-275
Detour route for closure of eastbound SR 60 between Tampa International Airport and I-275
Demolition of interstate 275 bridge over Memorial Blvd.