Project Details
Work Type Roadway Lighting Maintenance
Phase Construction
Limits Along US 19
Project Start Design Underway/Construction Starting Fall 2019
Length Various Locations
County
Road
Construction Cost $950,177.00
Estimated Completion Early 2020
Contractor Ajax Paving Industries of Florida
About

The Florida Department of Transportation's Design-Build Firm, Ajax Paving Industries of Florida, is making improvements to roadway lighting along US 19 from Flora Avenue to Puffin Lane in Pasco County. 

Improvements include installing new light poles and retrofitting existing light poles along the following segment of US 19: 

  • Flora Avenue to Alt US 19; nineteen retrofits
  • Alt US 19 to Mile Stretch Drive; nineteen retrofits
  • Mile Stretch Drive to Darlington Road; twenty-five retrofits and three new poles
  • Darlington Road to Sunray Drive; eleven retrofits
  • Gulf Drive to Cross Bayou Boulevard; ten retrofits
  • Cross Bayou Boulevard to Main Street; thirty retrofits
  • Main Street to Beau Lane; twenty-four retrofits
  • Jasmine Boulevard to Ranch Road/Hammock Road; twenty-three retrofits and one relocation
  • Ranch Road/Hammock Road to SR 52; forty-seven retrofits and two new poles 
  • SR 52 to Beacon Woods Drive; twenty-two retrofits
  • Beacon Woods Drive to Puffin Lane; fifty-two retrofits

Design is underway, construction is expected to start fall of 2019. 

View Factsheet
Contact Information
Construction Manager
Randall Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.