Project Details
Work Type Safety and Operational Improvements
Phase Construction
Limits North and south of SR 52
Project Start Design Underway/Construction to start fall of 2019
City
County
Road
Construction Cost $708,795
Estimated Completion Spring 2020
Contractor Ajax Paving Industries of Florida
About

The Florida Department of Transportation's Design-Build Firm, Ajax Paving Industries of Florida, is adding two median crossovers for official and emergency use in the existing I-75 median to the north (MM287) and south (MM 283.5) of SR 52 in Pasco County. 

This project is in the design phase, construction is expected to start fall of 2019.

View Factsheet
Contact Information
Construction Manager
Randall Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.