Project Details
Work Type Sidewalk
Phase Construction
Limits from Oscar Hill Rd to Dixie Hwy
Project Start Fall 2020
Length .3 miles
City
County
Road
Construction Cost $1,622,282
Estimated Completion Spring 2021
Contractor David Nelson Construction Co.
About

This project will add sidewalk along Alt. US 19 ( Pinellas Ave.) between Oscar Hill Road and Dixie Hwy in Tarpon Springs.  A new mid block pedestrian crossing with a rectangular rapid flashing beacon will also be installed between Anclote Road and Fulton Street.  

Construction activities are anticipated to begin in the fall of 2020 and be complete in the spring of 2021.

View Factsheet
Contact Information
Construction Manager
Sarah Gansz
727-575-8300
sarah.gansz@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.