Good Neighbor Trail in Downtown Brooksville along SR 50A, US 41 and Main St. 437264-2-52-01
Project Details
Work Type | Multi-use Trail |
---|---|
Phase | Construction |
Limits | meanders from west of SR 50 /SR 50A through downtown Brooksville to Main St./ Russell St. intersection |
Project Start | September 12, 2022 |
Length | 2.2 miles |
City | |
County | |
Road | |
Construction Cost | $20 million |
Estimated Completion | Summer 2024 |
Contractor | SEMA Construction, Inc. |
About
This project is building a 12 foot-wide paved multi-use trail in Brooksville.
This segment of the Good Neighbor Trail will be built from west of the intersection of SR 50 and SR 50A along SR 50A/Jefferson Street to and through Tom Varn Park, then along US 41/Broad Street to Main Street, along Main Street to Russell Street.
Construction began September 12, 2022 and is expected to be completed in summer 2024.
Project Updates
Southbound S Main Street has reopened!
Brooksville -- The southbound lane of S Main Street from E Liberty Street to south of Russell Street has reopened to traffic as of Saturday, December 2, 2023. All access is open, including roadway connections to S Main Street at Daniel, Lamar, and Hendrick avenues. Drivers can now travel in both directions of S Main Street. [The southbound lane closed June 8, 2023 for construction associated with the Good Neighbor Trail on the west side of S Main Street.]
Contact Information
Project Information |
---|
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.