Project Details
Work Type Repaving and Reconstruction
Phase Completed
Limits from east of SR 50A to west of Live Oak Drive
Length .33 miles
City
County
Road
About

THIS PROJECT WAS ACCEPTED ON TUESDAY, SEPTEMBER 24, 2018.  

The Florida Department of Transportation's contractor, Commercial Industrial Corporation, is repaving and reconstructing US 98/SR 50 (Cortez Boulevard) from east of SR 50A to the west of Live Oak Drive in Hernando County.

Improvements include:

  • Replacing sections of asphalt at the intersection with concrete to better handle the heavy truck traffic in this area
  • Repaving the remaining section of roadway with asphalt
  • Adding sidewalk to both sides of the roadway 

Motorists are advised that traffic shifts and lane closures will be required to build this project. Work requiring lane closures may occur nightly from 7:00 to 7:00 am. 

Electronic message boards will alert motorists to the upcoming closures. 

This $4.7 million project is anticipated to finish in fall of 2018. 

View Factsheet
Contact Information
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Project Images
SR 50 Aerial View New Concrete Roadway April 2018
SR 50 Aerial View New Concrete Roadway II April 2018
SR 50 Aerial View New Concrete Roadway II January 2018
SR 50 Aerial View New Concrete Roadway January 2018