Work Type Adding Westbound Right Turn Lane
Phase Completed
Limits At Success Drive/Corporate Center Drive
Length at intersection
City
County
Road
About

This project was partially accepted on July 14, 2018. 

The Florida Department of Transportation's contractor, Cone & Graham, Inc is adding a westbound right turn from SR 54 onto Success Drive/Corporate Center Drive in Odessa. 

The $313,083 project began June 2017 and is expected to finish in the summer of 2018. 