Operational Freight Improvements in Hillsborough and Pasco counties 254677-4-13-92
Project Details
Work Type | Operational Improvements |
---|---|
Phase | Completed |
Limits | 5 Locations in Hillsborough and Pasco counties |
City | |
County | |
Road |
About
THIS PROJECT WAS FINAL ACCEPTED ON AUGUST 19, 2020
This design-build project will provide operational improvements by modifying the turning radii for freight trucks at five locations in Hillsborough and Pasco counties.
Type of modifications and locations:
- SR 54 at Merchant Avenue in Pasco County: Modifying the median by extending the length of the eastbound turning radius from southbound Merchant Avenue onto eastbound SR 54.
To expedite this work, left-turn movements from Merchant Avenue onto SR 54 will be restricted for approximately 30 days, weather permitting. - US 301 at Mango Road in Hillsborough County: Improving the curve radius from northbound US 301 onto southbound Mango Road.
- US 98 at Old Lakeland Highway Frontage Road in Pasco County: Improving the curve radii from northbound Old Lakeland Highway Frontage Road onto eastbound US 98 and from westbound US 98 onto southbound Old Lakeland Highway Frontage Road.
- SR 60 at Bayport Drive in Hillsborough County: Modifying the striping and curve radius at northwest and southwest corners of SR 60 at Bayport Drive.
- SR 39 at SR 39A in Hillsborough County: Constructing a raised island in the median and adding a paved bulb-out for freight trucks making a northbound U-turn at this intersection.
Construction activities and lane closures will occur nightly from 8 p.m. to 6 a.m.
Construction is expected to finish during the summer of 2020.