SR 39 (James L Redman Parkway) Repaving from Charlie Griffin Rd to Alexander St. 445598-1-52-01
Project Details
Work Type | Repaving |
---|---|
Phase | Design |
Limits | from Charlie Griffin Rd to Alexander St. |
Length | .6 miles |
City | |
County | |
Road | |
Design Cost | $107,000 |
About
This project will repave SR 39 (James L. Redman Parkway) between Charlie Griffin Rd and Alexander St. in Plant City. It also includes adding a right turn lane on southbound James L. Redman Parkway onto westbound Alexander St. The existing right turn lane from Alexander St onto southbound James L. Redman Pkwy will also be widened.
The project is currently being designed. Construction is anticipated to begin in 2022.
View Factsheet
Contact Information
Design Manager |
---|
Michael MacKinnon
813-975-6431
Michael.mackinnon@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
|
Lane Closures
- There are no lane closures at this time.