EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type Safety Improvements
Phase Construction
Limits at Acline Drive
Project Start October 2020
City
County
Road
Construction Cost $293,864.00
Estimated Completion Early 2021
Contractor Ajax Paving Industries of Florida, LLC
About

The Florida Department of Transportation's contractor, Ajax Paving Industries of Florida, is making safety improvements to US 41 (50th Street) at Acline Drive in Tampa, Hillsborough County. 

Improvements include: 

  • extending the length of the southbound left-turn lane on US 41 (50th street) at Acline Drive

Construction has begun and is expected to finish in early 2021.

View Factsheet
Contact Information
Construction Manager
Randy Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.