Project Details
Work Type Safety Improvements
Phase Construction
Limits at Acline Drive
Project Start Design in underway/construction starts summer 2020
City
County
Road
Construction Cost $293,864.00
Estimated Completion Early 2021
Contractor Ajax Paving Industries of Florida, LLC
About

The Florida Department of Transportation's contractor, Ajax Paving Industries of Florida, is making safety improvements to US 41 (50th Street) at Acline Drive in Tampa, Hillsborough County. 

Improvements include: 

  • extending the length of the southbound left-turn lane on US 41 (50th street) at Acline Drive

Design is underway, construction is expected to start summer of 2020 and finish in early 2021.

View Factsheet
Contact Information
Construction Manager
Randy Aebersold
727-575-8300
Randall.Aebersold@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.