Project Details
Work Type ITS
Phase Construction
Limits from the Polk County line to Sand Lake Rd.
Project Start Early 2023
Road
Construction Cost $10.1 million
Estimated Completion Fall 2025
Contractor Traffic Management Solutions, Inc.
About

This project will install an ITS components in support of a connected vehicle infrastructure along I-4 between the Polk County line and Sand Lake Rd in Orange County.

Construction is anticipated to begin in early 2023 and be complete in the fall of 2025.