SR 594 (4th Street South) New On-ramp onto Westbound I-175 254677-3-30-01
Project Details
Work Type | New On-ramp Construction |
---|---|
Phase | Completed |
Limits | from 4th Avenue South to 6th Avenue South |
Length | n/a |
City | |
County | |
Road |
About
This project was accepted on August 3, 2017.
The FDOT is constructing a new on-ramp from northbound 4th Street South (SR 594) onto westbound I-175 in Pinellas County.
This new on-ramp, along with the existing southbound 4th Street South on-ramp, will provide access onto westbound I-175 from both directions of 4th Street South.
View Factsheet
Contact Information
Media Contact |
---|
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Lane Closures
- There are no lane closures at this time.