Project Details
Work Type Widening
Phase Construction
Limits from east of Curley Road to east of Morris Bridge Road
Project Start November 2017
Length 4.5 miles
City
County
Road
Construction Cost $42.5 million
Estimated Completion Summer 2021
Contractor D.A.B. Constructor, Inc.
About

This project will widen the existing two-lane road to a four-lane road with medians. A sidewalk will be built on the north side of the road and a 10-foot wide multi-use trail will be built on the south side. 

This $42.5 million project is expected to finish in the summer of 2021. 

FDOT hosts open house about reducing traffic and creating a diverging diamond in Pasco County

View Factsheet
Contact Information
Construction Manager
Zach Stringer
352-848-2600
Zachary.Stringer@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures

  • SR 54 widening from Curley Road to Morris Bridge Road
    Lane closures: Sunday, March 17 through Thursday, March 21 from 8 p.m. to 6:30 a.m.

     