Project Details
Work Type Resurfacing – Rigid Pavement Reconstruction
Phase Construction
Limits US 98/SR 50 at Mondon Hill Road / Spring Lake Hwy
Project Start May 18, 2026
Length 0.285 Miles
City
County
Road
Construction Cost $9.5 million
Estimated Completion spring 2027
Contractor Watson Civil Construction, Inc.
About

This project includes rigid pavement reconstruction of the US 98 / SR 50 intersection at Mondon Hill Road / Spring Lake Highway in the Brooksville area of Hernando County. The intersection will be reconstructed from asphalt to concrete pavement.

Additional improvements include asphalt resurfacing of the pavement approaches to the concrete area of the intersection, safety modifications, providing ADA compliant curb ramps, driveway reconstruction, minor drainage modifications, minor signalization work, signing and pavement markings, and lighting improvements.

Construction is underway as of May 18, 2026.

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • US 98 / SR 50 (Cortez Blvd.) approaching and through the intersection of Mondon Hill Road / Spring Lake Highway 
    Left lane closed each direction: Sunday, May 31 through Thursday, June 4 nights from 8 p.m. to 6:30 a.m. 

  • US 98 / SR 50 (Cortez Blvd.) approaching and through the intersection of Mondon Hill Road / Spring Lake Highway
    Left lane closed each direction: Tuesday, May 26 through Saturday, May 30 nights from 8 p.m. to 6:30 a.m.

Project Images
Unloading embankment material in the median of US 98 / SR 50 for temporary pavement construction (5-27-2026 photo)
Work has begun in the median of US 98 / SR 50 for temporary pavement construction (5-27-2026 photo)