US 98/SR 50 at Mondon Hill Road / Spring Lake Highway
- Project ID
- 447237-1-52-01
Project Details
- Work Type
- Resurfacing – Rigid Pavement Reconstruction
- Phase
- Construction
- Limits
- US 98/SR 50 at Mondon Hill Road / Spring Lake Hwy
- Project Start
- May 18, 2026
- Length
- 0.285 Miles
- City
- County
- Road
- Construction Cost
- $9.5 million
- Estimated Completion
- spring 2027
- Contractor
- Watson Civil Construction, Inc.
About
This project includes rigid pavement reconstruction of the US 98 / SR 50 intersection at Mondon Hill Road / Spring Lake Highway in the Brooksville area of Hernando County. The intersection will be reconstructed from asphalt to concrete pavement.
Additional improvements include asphalt resurfacing of the pavement approaches to the concrete area of the intersection, safety modifications, providing ADA compliant curb ramps, driveway reconstruction, minor drainage modifications, minor signalization work, signing and pavement markings, and lighting improvements.
Contact Information
-
Project Information
- Name:
- John McShaffrey
- Phone:
- 813-975-6930
- Email:
- john.mcshaffrey@dot.state.fl.us
-
Media Contact
- Name:
- Kayla Mejia
- Phone:
- 813-975-6060
- Email:
- Kayla.Mejia@dot.state.fl.us
Closures
-
US 98 / SR 50 (Cortez Blvd.) approaching and through the intersection of Mondon Hill Road / Spring Lake Highway
Lane closures: Sunday October 25 through Thursday, October 29 nights from 8 p.m. to 6:30 a.m.