View project: I-275 Widening from north of 38th Avenue N to north of 4th Street N
-
SR 694 (Gandy Boulevard) approaching and through the I-275 overpass
Lane closures: Monday, September 28 and Tuesday, September 29 nights from 8 p.m. to 5:30 a.m.
62nd Avenue N approaching and under the I-275 overpass
Right lane closed in each direction: Around-the-clock closures through approximately December 2026
62nd Avenue N approaching and under the I-275 overpass
Lane closures (eastbound): Sunday, September 27 through Thursday, October 1 nights from 8 p.m. to 5:30 a.m.
-
Southbound I-275 Exit 25 ramp to 38th Avenue N to close temporarily
St. Petersburg – Beginning early Monday morning, October 5, 2026, the southbound I-275 Exit 25 ramp to 38th Avenue N is scheduled to close for an extended period. The exit ramp is expected to be closed for widening, drainage, lighting, and other work for approximately 2 months. The ramp is estimated to reopen in mid-December, weather permitting.
The detour for the Exit 25 ramp closure will be signed to guide drivers as follows:
- DETOUR for southbound I-275 Exit 25 ramp to 38th Avenue N: Continue south on I-275 past Exit 25 and exit at 22nd Avenue N (Exit 24). At the bottom of the ramp, turn right and go west on 22nd Avenue N, then turn right onto US 19 (34th Street N) and go north to 38th Avenue N.
Detour Map
-
62nd Avenue N approaching and under the I-275 overpass
Right lane closed in each direction: Around-the-clock closures through approximately December 2026