US 301 from Lake St Charles to Progress Boulevard/Bloomingdale Avenue
Lane closures: Sunday, May 22 through Thursday, May 26 from 11 p.m. to 6 a.m. (northbound)
Lane closures: Sunday, May 22 through Thursday, May 26 from 9 a.m. to 2 p.m. and from 8 p.m. to 7 a.m. (southbound)
US 301 from I-75 to Progress Boulevard/Bloomingdale Avenue
Lane closures: Sunday, May 22 through Thursday, May 26 from 8 p.m. to 5 a.m. (northbound)
Lane closures: Sunday, May 22 through Thursday, May 26 from 10 p.m. to 7 a.m. (southbound)
Bloomingdale Avenue from US 301 to Duncan Road (part of the US 301 repaving project)
Lane closures: Sunday, May 22 through Friday, May 27 from 7:30 p.m. to 3:30 p.m. (eastbound)
Lane closures: Sunday, May 22 through Thursday, May 26 from 10 a.m. to 6:30 a.m. (westbound)
Progress Boulevard from US 301 to Farmington Oaks Place (part of the US 301 repaving project)
Lane closures: Sunday, May 22 through Thursday, May 26 from 12 a.m. to 11:59 p.m