Project Details

Work Type Rigid Pavement Reconstruction
Phase Construction
Limits SR 39 at Trapnell Road
Project Start Ocotber 13, 2025
Length .53 Mile
City
County
Road
Construction Cost $8 million
Estimated Completion Fall 2026
Contractor Webber, LLC

About

The Florida Department of Transportation (FDOT) is making improvements to the intersection of SR 39 and Trapnell Road in Hillsborough County, by replacing the intersection’s asphalt pavement with a durable concrete surface.

Message boards and signage are in place assisting drivers traveling through the area. Motorists are reminded to slow down, stay alert, and drive safely through the work zone.

Construction activities are expected to finish fall of 2026. 

View Factsheet The link target will open in a new tab.

Contact Information

Project Information
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us

Closures

  • There are no closures at this time.

Project Images

SR 39 at Trapnell Road performing roadway reflectivity testing (Photo July 2026)
SR 39 at Trapnell Road performing traffic signal inspection work (Photo July 2026)
SR 39 at Trapnell Road performing concrete grinding work (Photo July 2026)
SR 39 at Trapnell Road performing concrete work (Photo July 2026)
SR 39 at Trapnell Road performing roadway striping work (Photo July 2026)
SR 39 at Trapnell Road performing drainage work (Photo July 2026)
SR 39 at Trapnell Road performing median work (Photo June 2026)
SR 39 at Trapnell Road performing concrete quality control operations (Photo June 2026)
SR 39 at Trapnell Road showing concrete quality control operations (Photo June 2026)
SR 39 at Trapnell Road showing concrete grinding operations (Photo June 2026)
SR 39 at Trapnell Road showing concrete grinding operations (Photo June 2026)
SR 39 at Trapnell Road showing concrete grinding operations (Photo June 2026)
SR 39 at Trapnell Road showing concrete grinding operations (Photo June 2026)
SR 39 highway lighting installation work (Photo June 2026)
SR 39 at Trapnell Road showing concrete grinding operations (Photo June 2026)
SR 39 at Trapnell Road looking east showing grade work along median (Photo May 2026)
SR 39 at Trapnell Road looking south showing conduit installation work (Photo May 2026)
SR 39 at Trapnell Road looking south showing drainage structure installation work (Photo May 2026)
SR 39 at Trapnell Road looking east at recently opened intersection showing new concrete travel lanes (Photo April 2026)
SR 39 at Trapnell Road looking west at recently opened intersection showing new concrete travel lanes (Photo April 2026)
SR 39 at Trapnell Road crews paving travel lanes approaching the intersection (Photo April 2026)
SR 39 at Trapnell Road intersection looking northwest at milling operations (Photo March 2026)
SR 39 at Trapnell Road preparing roadway for concrete (April 2026)
SR 39 at Trapnell Road showing completed grading and rolling activities (Photo April 2026)
SR 39 looking north at southbound lanes crews performing milling operations (Photo March 2026)
SR 39 looking northbound at shoulder widening activities to the south side of the Trapnell Rd (Photo March 2026)
SR 39 north of Trapnell Rd looking north at highway lighting relocation work (Photo March 2026)
SR 39 at Trapnell Road in Plant City looking east (February 2026)
SR 39 at Trapnell Road in Plant City looking north (Photo February 2026)
SR 39 north of Trapnell Road in Plant City looking north (Photo February 2026)
SR 39 at Trapnell Road in Plant City looking north (Photo February 2026)
SR 39 looking west toward Trapnell Road in Plant City (Photo February 2026)
SR 39 looking south toward Trapnell Road in Plant City (Photo February 2026)
SR 39 just south of Trapnell Road in Plant City (Photo February 2026)
SR 39 at Trapnell Road in Plant City looking west (Photo February 2026)
SR 39 at Trapnell Road in Plant City looking north (Photo February 2026)
Trapnell Rd to the east of SR 39 in Plant City Opened to Traffic on Feb 10, 2026
Trapnell Rd to the east of SR 39 in Plant City Opened to Traffic on Feb 10, 2026
Trapnell Rd to the east of SR 39 in Plant City Opened to Traffic on Feb 10 2026
Newly poured concrete median on US 301 and Trapnell Road in Plant City (January 2026 photo)
Crew preparing roadway for concrete pour of northbound US 301 travel lanes just south of Trapnell Road in Plant City (January 2026 photo)
Crews removing and replacing sections of sidewalk along the east side of SR 39 (January 2026)
Crews prepare roadway for concrete pavement of northbound travel lanes on SR 39 (January 2026)
Construction equipment replacing and relocating drainage inlet on the east side of SR 39 to the north of Trapnell Road (January 2026)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (December 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (December 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (December 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (December 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (December 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (December 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (November 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (November 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (November 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (November 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (November 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (November 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (November 2025)
SR 39 Intersection Pavement Reconstruction at Trapnell Road (November 2025)