Project Details
Work Type New Traffic Signal
Phase Construction
Limits at N 12th Street
Project Start Summer 2025
City
County
Road
Estimated Completion Summer 2026
Contractor Cone & Graham, Inc.
About

This construction project is addressing safety improvements with the construction of a new traffic signal on SR 574 (W Martin Luther King Jr Boulevard) at N 12th Street in Hillsborough County. 

Elements of work shall include, but are not limited to, installation of the signal, roadway resurfacing, and sidewalk, pedestrian and lighting improvements.

Construction activities are underway and expected to be complete in summer 2026.

*********************************************************************************

What is design-build? Design-build is a method of project delivery in which one entity - the design-build team - works under a single contract with the FDOT (or any owner) to fully design and construct a project.  The contract work covers from initial design through construction completion.  This contract type typically allows for faster construction of a project as design and construction can be on-going simultaneously. 

View Factsheet
Contact Information
Project Information
Maddie Griffin
727-575-8334
Maddie.Griffin@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Closures
  • SR 574 (W Martin Luther Jr. Boulevard) at N 12th Street
    Lane Closures: Monday, May 11 through Friday, May 15 from 8 a.m. to 6 p.m.
    Night lane closures: Sunday, May 10 through Thursday May 14 nights from 7 p.m. to 12 a.m.

Project Images
Pouring raised concrete areas (March 2026 photo)
Installing mast arm cap (March 2026 photo)
Replacing the existing fiber pull box (March 2026 photo)
Upright and mast arm transport (February 2026 photo)
Wiring stoplights (February 2026 photo)
Assembling the mast arm (February 2026 photo)
Pouring cantilever ground mounted sign spread footing (February 2026 photo)
Grouting for structural support (February 2026 photo)
Flying upright at SW corner at southwest corner of MLK and 12th Street (February 2026 photo)
Forming the sidewalk, curb & gutter at the SW corner (February 2026 photo)
Newly installed sidewalk (January 2026 Photo)
Performing cleanup operation (January 2026 Photo)
Removing old sections of sidewalk, curb and gutter (January 2026 Photo)
Loading and hauling away concrete debris (January 2026 Photo)
Installing & tying in conduit runs at SW corner of Nebraska Avenue and E 124th Avenue (January 2026 Photo)
Backfilling conduit runs at SW corner of Nebraska Avenue and E 124th Avenue (January 2026 Photo)