I-75 Concrete Bridge Deck Repairs over the Alafia River Bridge and Other Locations 445828-1-52-01, 445833-1-52-01
Project Details
Work Type | Concrete Bridge Rehabilitation |
---|---|
Phase | Construction |
Limits | Over the Alafia River Bridge and Other Locations |
Project Start | Fall 2024 |
City | |
County | |
Road | |
Construction Cost | $1.7 million |
Estimated Completion | Fall 2025 |
Contractor | Bridge Masters Construction, LLC |
About
This project is making repairs and replacing the concrete pavement along Interstate 75 roadway over the Alafia River Bridge and other locations (SB Hillsborough River Bridge, Ashley Street On-Ramp over Laurel Street, and NB I-275 to NB I-75) throughout Hillsborough County.
Construction activities will occur during daytime and nighttime hours.
Work requiring lane closures will occur at night from 9 p.m. to 5 a.m.
Please use caution when traveling through the work zone and remain alert for construction workers.
This project is expected to finish during fall of 2025.
Contact Information
Project Information |
---|
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.