Project Details

Work Type
Safety Improvements
Phase
Construction
Limits
from SR 60 (Adamo Drive) to US 41/50th Street
Project Start
June 9, 2025
Length
3.75 miles
City
County
Road
Construction Cost
$480,000
Estimated Completion
Summer 2026
Contractor
Cone & Graham, Inc.

About

The Florida Department of Transportation's Design-Build firm, Cone & Graham, Inc., is making roadway lighting improvements to US 41B (Causeway Boulevard) from SR 60 (Adamo Drive) to US 41/50th Street in Hillsborough County.

Safety improvements include installing new light poles and retrofitting existing light poles along USB 41.

Construction activities are expected to be complete in summer 2026. 

*********************************************************************************

What is design-build? Design-build is a method of project delivery in which one entity - the design-build team - works under a single contract with the FDOT (or any owner) to fully design and construct a project.  The contract work covers from initial design through construction completion.  This contract type typically allows for faster construction of a project as design and construction can be on-going simultaneously. 

View Factsheet The link target will open in a new tab.

Contact Information

Closures

  • There are no closures at this time.