Highland Avenue Corridor Improvements from Violet Street to US 92 (Hillsborough Avenue) 440511-4-52-01
Project Details
| Work Type | Urban Corridor Improvements |
|---|---|
| Phase | Design |
| Limits | Highland Avenue from Violet Street to US 92 (Hillsborough Avenue) |
| Length | 0.3 miles |
| City | |
| County | |
| Road |
About
This project will improve the urban corridor on Highland Avenue from Violet Street to US 92 (Hillsborough Avenue) in Tampa.
Key improvements within the project limits include:
- Add 8 foot sidewalk along the western side of Highland Avenue
- Adding a crosswalk at Wilder Avenue
- Adding a crosswalk at Giddens Avenue
- Restore roadway pavement
- Upgrading the corridor lighting, ADA, pavement markings, and signage
Construction is currently anticipated to begin in late 2027.
View Factsheet The link target will open in a new tab.
Contact Information
Design Manager
Carlos Perez
813-975-6929
CarlosH.Perez@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us