Project Details
Work Type Resurfacing
Phase Construction
Limits north of CR 491 to north of Landfill Rd
Project Start November 25, 2025
Length 2.5 miles
City
County
Road
Construction Cost $3.5 million
Estimated Completion Summer 2026
Contractor Superior Asphalt, Inc.
About

This project is milling and resurfacing US 98 (Ponce De Leon Blvd.) from north of CR 491 to north of Landfill Road. Pavement striping, signage, and other minor work items are also part of this project.

Construction is underway as of November 25, 2025.

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
John.McShaffrey@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • US 98 from north of CR 491 (Citrus Way) to north of Landfill Road
    Lane closures/flagging operations: Monday, March 30 through Friday, April 3 from 6:30 a.m. to 6:30 p.m.

  • US 98 from north of CR 491 (Citrus Way) to north of Landfill Road
    Lane closures/flagging operations: Saturday, March 28 from 6:30 a.m. to 6:30 p.m.

Project Images
New signs are being installed within the US 98 resurfacing project limits (3-12-2026 photo)
Black base asphalt is compacted around the rebuilt traffic separator at the Landfill Road intersection (3-5-2026 photo)
Shoulder work along US 98 (2-16-2026 photo)
Drainage pipe extension work along US 98 (2-5-2026 photo)
Milling old asphalt on US 98 in preparation to place new asphalt (1-19-2026 photo)
Paving new asphalt on US 98 (1-19-2026 photo)