US 41 and 56th Street (SR 583) Bridge Maintenance in Hillsborough County 449982-1-52-01
Project Details
| Work Type | Bridge Maintenance |
|---|---|
| Phase | Construction |
| Project Start | February 6, 2026 |
| City | |
| County | |
| Road | |
| Construction Cost | $2.9 million |
| Estimated Completion | Summer 2027 |
| Contractor | Seminole Equipment, Inc |
About
This project is performing routine maintenance activities to the US 41 and 56th Street (SR 583) bridges over Hillsborough River in Tampa and Temple Terrace, Hillsborough County.
Construction activities are expected to finish during the summer of 2027.
View Factsheet The link target will open in a new tab.
Contact Information
Project Information
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
-
US 41 (Nebraska Avenue) over Hillsborough River
Lane closures: Monday, July 20, and Tuesday July 21, from 10:30 a.m. to 8:30 p.m. -
US 41 (Nebraska Avenue) over Hillsborough River
Lane closures: Monday, July 13 through Saturday July 18, from 10:30 a.m. to 8:30 p.m.