Project Details

Work Type
Safety Improvements
Phase
Construction
Limits
from Old US 41-A to Bloomingdale Avenue
Project Start
September 2, 2026
City
County
Road
Construction Cost
$894,000
Estimated Completion
Summer 2027
Contractor
Cone & Graham, Inc.

About

The Florida Department of Transportation's Design-Build Firm, Cone & Graham, Inc., is making roadway improvements to US 41 (S Tamiami Trail) from Old US 41-A to Bloomingdale Avenue in Hillsborough County.

Elements of work shall include but are not limited to roadway milling and resurfacing with a high surface friction treatment. These improvements will protect against skidding and provide a safe travel path for vehicles.

Construction activities are expected to be complete in summer of 2027.

*********************************************************************************

What is design-build? Design-build is a method of project delivery in which one entity - the design-build team - works under a single contract with the FDOT (or any owner) to fully design and construct a project.  The contract work covers from initial design through construction completion.  This contract type typically allows for faster construction of a project as design and construction can be on-going simultaneously. 

View Factsheet The link target will open in a new tab.

Contact Information

Closures

  • US 41 (S Tamiami Trail) at Bloomingdale Avenue