Project Details

Work Type Repaving
Phase Construction
Limits Bruce B Downs Blvd to 50th Street
Project Start Late 2026
City
County
Road
Construction Cost $10.3 million
Estimated Completion Fall 2027
Contractor Preferred Materials, Inc

About

This project is repaving SR 582 (Fowler Avenue) from Bruce B. Downs Boulevard to 50th Street in Temple Terrace (Tampa), Hillsborough County. 

Other improvements include:

  • adding wide bike lane enhancements
  • installing two midblock pedestrian signals at 14th Street and 17th Street
  • constructing a new wide sidewalk
  • adding a 14-ft. wide paved emergency access connection from the FDOT District 7 Headquarters (McKinley Drive to 46th Street)

Construction activities are expected to begin late 2026. 

View Factsheet The link target will open in a new tab.

Contact Information

Project Information
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us

Closures

  • There are no closures at this time.