I-4 Westbound Interchange Improvements from Orient Road to west of I-75 430337-1-52-01
Project Details
Phase | Design |
---|---|
Limits | From Orient Road to west of I-75 |
City | |
County | |
Road | |
Design Cost | $5 million |
About
This project will add new ramps and widen the existing westbound collector/distributor road between I-75 and US 92(Hillsborough Avenue) in Hillsborough County.
The westbound Hillsborough Avenue flyover ramp and bridge will also be replaced.
This project is currently being designed.
Construction is currently not funded at this time.