Project Details
Work Type Widening
Phase Completed
Limits From Lockhart Road to east of Remington Road
City
County
Road
About

Construction was completed and accepted from the contractor on May 11, 2021.

This project widened SR 50 (Cortez Road) from Lockhart Road to east of Remington Road from four to six lanes. Bike lanes, sidewalk, and highway lighting were also included in the construction.

The median at Remington Road was closed and relocated approximately 200 feet to the west.  The new median opening was constructed with a raised concrete curb, restricting left turn movements from adjacent properties.

 

View Factsheet
Contact Information
Media Contact
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Closures
  • There are no closures at this time.
Project Images
Looking east at construction winding down along SR 50 near Remington Road (3/31/2021 photo)
Looking east along SR 50 near the west end of the project at Braewood Street (3/31/2021 photo)
Looking west at construction nearing completion on SR 50 near Remington Road (3/31/2021 photo)
Moving drainage pipe for installation along westbound SR 50 near Remington Road (October 26, 2020 photo)
Moving drainage pipe for installation along westbound SR 50 near Remington Road (October 26, 2020 photo)
Excavating for pipe installation along SR 50 (October 26, 2020 photo)
Moving pipe along SR 50 (October 26, 2020 photo)
Drainage pipe stockpile along westbound SR 50 (October 26, 2020 photo)
Moving and installing drainage pipe along westbound SR 50 (October 26, 2020 photo)
Construction along eastbound SR 50 approaching I-75 (October 26, 2020 photo)