Henry Canal Drainage Improvements from Hoover Boulevard to Anderson Road 422929-4-52-01
Project Details
Work Type | Drainage Improvements |
---|---|
Phase | Completed |
Limits | From Hoover Boulevard to Anderson Road |
Length | 2600 feet |
City | |
County |
About
THIS PROJECT WAS ACCEPTED ON NOVEMBER 15, 2019
The $3.9 million project will re-grade and stabilize the canal slopes for a distance of approximately 2600 feet along the Henry Canal from Hoover Boulevard to Anderson Road in Hillsborough County.
Improvements will resolve the slope stability and erosion issues along the drainage canal.
Construction is expected to finish in the fall of 2019.
View Factsheet
Contact Information
Media Contact |
---|
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.