Project Details
Work Type Access Improvements
Phase Construction
Limits from Columbus Drive to CSX Intermodal Center
Project Start Early 2023
Length .5 miles
City
County
Construction Cost $6 million
Estimated Completion Late 2023
Contractor Watson Civil Construction, Inc.
About

The Florida Department of Transportation's contractor, Watson Civil Construction, Inc., is repaving North 62nd Street from E. Columbus Drive to the CSX Intermodal Center in Tampa. 

Other improvements include replacing the existing drainage ditch with a closed reinforced concrete pipe system, adding bike lanes, and installing sidewalk.  

Construction is anticipated to begin in early 2023 and be complete by end of 2023. 

To receive construction updates and traffic alerts via email, be sure to subscribe by visiting the project webpage at FDOTtampabay.com 

Please note: that pre-construction activities have begun along the project limits and will continue over the coming months (July/August). For safety reasons, the FDOT asks that all vehicles refrain from parking/staging on either side of 62nd Street N. to the south of Broadway Avenue. Thank you! 

View Factsheet
Contact Information
Construction Manager
Syeda Zaidi
813-612-3200
Syeda.Zaidi@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.