SR 50 Good Neighbor Trail Connector from west of Suncoast Parkway to Cobb Road/SR 50 (Cortez Boulevard) 435720-1-52-01
Project Details
Work Type | Multi-use Trail |
---|---|
Phase | Construction |
Limits | From west of Suncoast Parkway to Cobb Rd |
Project Start | July 2020 |
City | |
County | |
Road | |
Construction Cost | $5,526,496 |
Estimated Completion | Fall 2021 |
Contractor | Watson Civil Construction, Inc. |
About
This project will create a 12 foot wide paved shared use path along SR 50 between the Suncoast Parkway and the SR 50/ Cobb Road intersection.
Construction is underway and is expected to be completed in the fall of 2021.
View Factsheet
Contact Information
Construction Manager |
---|
Cleo Babb
352-848-2600
cleo.babb@dot.state.fl.us
|
Media Contact |
John McShaffrey
813-975-6930
John.Mcshaffrey@dot.state.fl.us
|
Lane Closures
-
SR 50 (Cortez Boulevard) from west of Wiscon Road to Cobb Road
Lane closure (eastbound only 24 hours/day) through approximately the end of March 2021 -
SR 50 (Cortez Boulevard) from B.W. Stevenson Road to Winter Street
Lane closure (westbound only 24 hours/day) through approximately the end of March 2021