Project Details
Work Type Multi-use Trail
Phase Construction
Limits From west of Suncoast Parkway to Cobb Rd
Project Start July 2020
City
County
Road
Construction Cost $5,526,496
Estimated Completion Fall 2021
Contractor Watson Civil Construction, Inc.
About

This project will create a 12 foot wide paved shared use path along SR 50 between the Suncoast Parkway and the SR 50/ Cobb Road intersection.

Construction is underway and is expected to be completed in the fall of 2021.

View Factsheet
Contact Information
Construction Manager
Cleo Babb
352-848-2600
cleo.babb@dot.state.fl.us
Media Contact
John McShaffrey
813-975-6930
John.Mcshaffrey@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Project Images
Grading lime rock for construction of the trail base (5/6/2021 photo)
Moving lime rock for construction of the trail base (5/6/2021 photo)
A portion of the new trail has been paved and sodded on the south side of SR 50 (5/6/2021 photo)
Some of the new trail has been paved on the south side of SR 50 (5/6/2021 photo)
Some of the new trail has been paved on the south side of SR 50 (5/6/2021 photo)
Trail construction on the south side of SR 50 (5/6/2021 photo)
Construction of road base for the trail on the south side of SR 50 (5/6/2021 photo)
Earthwork for the trail on the south side of SR 50 (5/6/2021 photo)
Drainage pipes have been installed next to existing sidewalk (December 8, 2020 photo)
Installing drainage pipes next to SR 50 (December 8, 2020 photo)
Leveling the area where pipe has been installed (December 8, 2020 photo)
Drainage pipes are inspected by video (November 16, 2020 photo)
Drainage work adjacent to SR 50 (November 11, 2020 photo)
Drainage work along SR 50 (November 2, 2020 photo)