Project Details
Work Type Multi-use Trail
Phase Construction
Limits From west of Suncoast Parkway to Cobb Rd
Project Start July 2020
City
County
Road
Construction Cost $5,526,496
Estimated Completion Fall 2021
Contractor Watson Civil Construction, Inc.
About

This project will create a 12 foot wide paved shared use path along SR 50 between the Suncoast Parkway and the SR 50/ Cobb Road intersection.

Construction is underway and is expected to be completed in the fall of 2021.

View Factsheet
Contact Information
Construction Manager
Cleo Babb
352-848-2600
cleo.babb@dot.state.fl.us
Media Contact
John McShaffrey
813-975-6930
John.Mcshaffrey@dot.state.fl.us
Lane Closures
  • SR 50 (Cortez Boulevard) from west of Wiscon Road to Cobb Road
    Lane closure (eastbound only 24 hours/day) through approximately the end of July 2021

  • SR 50 (Cortez Boulevard) from B.W. Stevenson Road to Winter Street
    Lane closure (westbound only 24 hours/day) through approximately the end of July 2021

Project Images
Drainage pipes have been installed next to existing sidewalk (December 8, 2020 photo)
Installing drainage pipes next to SR 50 (December 8, 2020 photo)
Leveling the area where pipe has been installed (December 8, 2020 photo)
Drainage pipes are inspected by video (November 16, 2020 photo)
Drainage work adjacent to SR 50 (November 11, 2020 photo)
Drainage work along SR 50 (November 2, 2020 photo)