Project Details
Work Type Arterial Traffic Management System
Phase Construction
Limits City of Tampa
Project Start October 2020
City
County
Construction Cost $38,345,345
Estimated Completion Summer 2024
Contractor Traffic Control Devices, Inc.
About

The design-build project will upgrade 402 signals and install 98 miles of new fiber conduit and other communication components to enhance the connectivity of the traffic signals throughout the City of Tampa. 

This project has begun and is expected to finish in the summer of 2024.

This contract combines work included from projects 424213-3,424213-4 and 424213-6 into a single construction contract.

View Factsheet
Contact Information
Construction Manager
Anna Geismar
813-975-3553
Anna.Geismar@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • SR 574 (Dr. Martin Luther King Jr. Blvd.) from Ridge Avenue to 40th Street
    Lane closures: Monday, April 19 through Friday, April 23 from 9:00 a.m. to 3:00 p.m.

    21st Street from Adamo Drive to east 17th Street
    Lane closures: Monday, April 19 through Friday, April 23 from 9:00 a.m. to 3:00 p.m.

Project Images
Traffic Management System - City of Tampa Arterials (March 2021)
Traffic Management System - City of Tampa Arterials (March 2021)
Traffic Management System - City of Tampa Arterials (March 2021)
Traffic Management System - City of Tampa Arterials (March 2021)