Project Details
Work Type Weigh Station access improvements
Phase Construction
Limits eastbound weigh station to McIntosh Rd exit
Project Start September 2020
City
County
Road
Construction Cost $2,651,273
Estimated Completion Spring 2021
Contractor C.W. Roberts Contracting, Inc.
About

This project is extending the eastbound merge lane from the I-4 weigh-in-motion station and extending the eastbound McIntosh Road exit ramp by 300 ft. in eastern Hillsborough County.

Construction activities have begun and are expected to finish in the spring of 2021.

View Factsheet
Contact Information
Construction Manager
Jessica Lyons
813-612-3200
Jessica.Lyons@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • I-4 from eastbound weigh station to McIntosh Road
    Lane closures: Sunday, November 1 through Thursday, November 5 from 9 p.m. to 5 a.m.