Project Details
Work Type Repaving
Phase Construction
Limits from north of 15th Ave. to south of Bullfrog Creek
Project Start November 25, 2021
Length 8.5 miles
City
County
Road
Construction Cost $25.6 million
Estimated Completion Summer 2024
Contractor Preferred Materials, Inc.
About

The Florida Department of Transportation is replacing the asphalt pavement with a durable concrete surface at US 41 (Tamiami Trail) and Big Bend Road (CR 672) in Hillsborough County. This intersection will be reconstructed in phases and is to finish by late 2022, weather permitting.

In addition to the intersection improvements, this project is repaving approximately 8.5 miles of roadway between 15th Avenue and Bullfrog Creek, adding a sidewalk along the west side of US 41, and connecting existing sidewalks on the east side of US 41 from bus stops to nearby intersections.

Access to businesses, side streets, and emergency vehicles to be maintained. Advanced warning signs and message boards are assisting motorists traveling through this area.

Motorists should allow extra travel time as significant traffic delays may occur along this stretch of US 41. 

The $25.6 million project is estimated to finish by the summer of 2024. 

To receive construction updates and traffic alerts via email, subscribe above.

View Factsheet
Contact Information
Construction Manager
Andrew Williams
813-612-3200
Andrew.Williams@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • US 41 (Tamiami Trail) from 19th Ave to Symmes Road  
    Lane closures: Tuesday, July 5 through Friday, July 8 from 9 a.m. to 4 p.m. (northbound and southbound)

Project Images
US 41 (Tamiami Trail) Repaving from 15th Ave to Bullfrog Creek (May 2022)
US 41 (Tamiami Trail) Repaving from 15th Ave to Bullfrog Creek (May 2022)
US 41 (Tamiami Trail) Repaving from 15th Ave to Bullfrog Creek (May 2022)