Project Details
Work Type Repaving
Phase Construction
Limits from north of 15th Ave. to south of Bullfrog Creek
Project Start November 25, 2021
Length 8.5 miles
City
County
Road
Construction Cost $25.6 million
Estimated Completion Summer 2024
Contractor Preferred Materials, Inc.
About

This project is repaving US 41 (Tamiami Trail) between 15th Avenue and Bullfrog Creek in Apollo Beach.  

In addition, the asphalt pavement at the intersection of US 41 and Big Bend Road is to be removed and replaced with a durable concrete surface. 

Other roadway improvements include:

  • adding sidewalk along the west side of US 41
  • connecting sidewalks from bus stops to nearby intersections along the east side of US 41  

Construction activities are expected to finish summer of 2024.

View Factsheet
Contact Information
Construction Manager
Andrew Williams
813-612-3200
Andrew.Williams@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.